As part of the task, we performed work on the Olefin II installation, consisting of, among others, to:
– dismantling of 3 long-serving pyrogas coolers with a total weight of 68,000 kg and ascending and descending pipelines connecting the pyrogas coolers with a vapor separator
– assembly of 3 new generation pyrogas coolers with a total weight of 66300 kg and ascending and descending pipelines connecting pyrogas coolers with a vapor separator.